Inspections Required, Permit Process
| The
General Contractor or the person that the Building Permit was issued to
must make all inspection requests.
(Footings, Foundations, Rough-Ins, Insulation, and Final for C.O.).
Electrical, Plumbing & Mechanical Contractors will be responsible
to notify the General Contractor when ready for Rough-In, Final, and other
inspections. |
|
| A
minimum of one (1) day notice is required for all inspections. |
|
| All
inspections must be called in by the correct address and permit number. |
|
| Building Permit Cards must be posted and building plans must be available at the jobsite or the inspection will not be performed and a $50.00 PENALTY FEE WILL BE CHARGED. | |
| Inspection results will be recorded with the permit card. | |
| Calls to the inspection department concerning the status of inspections are discouraged. Check permit card at jobsite for inspection results. | |
| Priorities
for daily inspections will be as follows: |
|
| 1.
Concrete pours. (i.e.
footing and slabs). |
|
| 2.
Open ditches that are a potential danger to the public. (i.e. water & sewer lines and underground electrical) |
|
| 3.
Foundations. |
|
| 4.
Restoration of Electrical Service to existing buildings. |
|
| 5.
Mechanical Change-Outs / Repairs during extreme weather conditions. |
|
| TEMPORARY POLE INSPECTION | |
| To
be made in conjunction with the Footing or Foundation Inspection.
In order to erect a temporary pole prior to a footing or foundation
inspection an electrical permit for the temporary pole must be obtained. |
|
| FOOTING INSPECTION | |
| To
be made after the trenches are excavated, all grade stakes are installed,
all reinforcing steel and supports are in place an appropriately tied,
all necessary forms are in place and braced and before any concrete is
placed. Setbacks will be
checked for conformance to the zoning ordinance. |
|
| BUILDING FRAMING | |
| To
be made after roof, wall ceiling and floor framing is complete with appropriate
blocking, bracing and fire
stopping in place. The following
items must be in place and visible for inspection: |
|
|
1. Pipes; |
|
|
2. Chimneys and vents; |
|
|
3. Flashing for roofs, chimneys and wall openings; |
|
| 4. Insulation baffles; | |
| 5. All lintels required to be bolted to the framing for support shall not be covered by any exterior or interior wall or ceiling finish material before approval. Work may continue without approval for lintels supported on masonry or concrete. | |
| UNDER SLAB INSPECTION, AS APPROPRIATE | |
| “… all electrical, plumbing and/or heating and air conditioning facilities… is installed when required but before any concrete is placed” | |
| SLAB INSPECTION, AS APPROPRIATE | |
| To be made after all forms as have been placed, all electrical, plumbing and/or heating and air conditioning facilities, all crushed stone, a vapor barrier, all reinforcing steel with supports and ties and/or all welded wire fabric is installed when required but before any concrete is placed | |
|
|
Exception:
Inspection is not required for driveway slabs, carport slabs, patio slabs, walks, etc., which are considered as non-habitable
spaces. |
| FOUNDATION INSPECTION, WOOD FRAME CONSTRUCTION | |
| To
be made after all foundation supports are installed.
This inspection is to check foundation supports, crawl space leveling,
and ground clearances. |
|
| OPEN FLOOR INSPECTION | |
| To be made after crawl space has been graded and floor system framing has been installed and prior to sub-floor having been installed. This inspection is to check girder for compliance of size, spacing, centering, blocking, etc. | |
| ROUGH-IN INSPECTION | |
| When
all building framing and parts of the electrical, plumbing or heating-ventilation
or cooling system that will be hidden from view in the finished building
have been placed but before any wall, ceiling finish or building insulation
is installed. |
|
| **NOTE:
When a construction project requires all four disciplines, i.e.,
Building, Electrical, Plumbing and Mechanical installations, each discipline
will be inspected simultaneously, during one inspection trip.
Inspection requests should not be made unless each discipline is
ready for a rough-in inspection. |
|
| Framing
Rough-In |
|
| To be made after roof, wall ceiling and floor framing are complete with appropriate bricking, bracing and fire stopping in place. The following items must be in place and visible for inspection: | |
| 1. Pipes; | |
| 2.
Chimneys and vents; |
|
| 3.
Flashing for roofs, chimneys and wall openings; |
|
| 4.
Insulation baffles; |
|
| 5.
All lintels required to be bolted to the framing for support and
shall not be covered by any exterior or interior wall or ceiling finish
material before approval. Work
may continue without approval for lintels supported on masonry or concrete. |
|
| Electrical
Rough-In |
|
|
After
all wiring has been installed, all joints properly made, all switches
and cabinets installed. Firestopping and Draftstopping must be installed; |
|
| Plumbing
Rough-In |
|
|
After
all piping is installed and all joints properly made; Drain
and supply lines installed; Firestopping,
draftstopping and rodent proofing as necessary; Pressure
test on water distribution piping must be a minimum of 100 psi; All
underground piping must be inspected for proper burial depth before
being covered. |
|
| Mechanical
Rough-In |
|
|
When
mechanical boots are installed; Supply
and return duct (where it will be enclosed) installed; Drains
and refrigerant lines installed in areas to be enclosed; Gas
piping installed with 15 psi minimum test; Venting
for gas appliances installed. |
|
| Pre-Fab
Fireplace Rough-In |
|
|
Unit installed per manufacturer’s instructions with vent installed; Hearth thermal protection installed and protected. |
|
| INSULATION INSPECTION | |
| To
be made after an approved building framing and rough-in inspection, with
all insulation and vapor retarders in place but before any wall or ceiling
covering is applied. |
|
| WATER/SEWER LINE INSPECTION | |
| After
lines from the house to the water/sewer tap are installed, connected,
and before covering. |
|
| CERTIFICATE OF OCCUPANCY | |
| **NOTE: When a construction project requires all four disciplines, i.e., Building, Electrical, Plumbing and Mechanical installations, each discipline will be inspected simultaneously, during one inspection trip. Inspection requests should not be made unless each discipline is ready for a final inspection. | |
| Building
Final |
|
| After all construction is completed and street numbers are installed; Floor-ceiling insulation installed. | |
| Electrical
Final |
|
| After all fixtures are in place and properly connected, including heating unit, air conditioning, water heater and all fans. | |
| Plumbing
Final |
|
| After all fixtures
are in |
|
| Mechanical
Final |
|
| When all units are in place and properly connected & vented. | |